Rail Pits | Premier Pits https://www.premierpits.com Garage Pits Wed, 15 Mar 2023 11:05:31 +0000 en-GB hourly 1 https://wordpress.org/?v=5.8.10 Holgate Depot Case Study https://www.premierpits.com/portfolio-posts/holgate/ Wed, 15 Mar 2023 10:54:59 +0000 https://www.premierpits.com/?post_type=portfolio&p=2160 Premier Pits was appointed in October 2016 to install a prefabricated vehicle pit. The original scope was to install the pit with in situ reinforced concrete.

The post Holgate Depot Case Study first appeared on Premier Pits.]]>

The Project

Premier Rail Pits were appointed by Story Contracting in 2019, with the
project consisting in the supply and installation of 3no inspection pits at
Network Rail Route Services’ Holgate Depot in York. Network Rail required the additional pits due to an increase in maintenance activity required within the depot.

The Problem

Due to the depot being operational during the upgrade works, Story sought to find a solution for the pits to keep disruption to a minimum.

Solution

After a consultation period discussing the design, Premier Rail Pits were
able to supply a commercially competitive product when compared to
traditional in situ poured concrete methods, by drastically reducing onsite
time, and offering a long-term watertight product which is easy to
maintain and clean. All rail fixings, LED lighting, air points and access steps
were installed in the pits prior to delivery to site, further reducing the
duration of the project. Once installed, all lighting, including emergency
lights, were connected by Premier Rail Pits as part of the works.

Client Details

Client: Story Contracting Ltd

Location: Network Rail Route Services

Specification

Captive nuts in place for mounting rails
Fully fitted with all services including
LED lights
Finish – Internal shot blasted, painted to Premier Rail Pits specification
Manufactured to strict tolerances
Anti-slip Stairs at each end
Entry and exit tunnels
Spillage sump at each end
Reinforcing mesh fitted to the pit prior to delivery

Rail Pit Design Standards

BS EN 1991 Loadings
BS EN 1993 Structural Steelwork design
BS8500 & BS EN 206 Concrete Specifications
NR/L2/TRK/2102 – Issue 7 Design and Construction of Track
NR/GN/CIV/025 Structural Assessment of Underbridges

No helpful answer? Call our support team.

+44 (0) 1775 821222

The post Holgate Depot Case Study first appeared on Premier Pits.]]> Railway Technology Centre Case Study https://www.premierpits.com/portfolio-posts/railway-technology-centre-case-study/ Fri, 15 Sep 2017 15:08:07 +0000 https://www.premierpits.com/?post_type=portfolio&p=1447 Premier Pits was appointed in October 2016 to install a prefabricated vehicle pit. The original scope was to install the pit with in situ reinforced concrete.

The post Railway Technology Centre Case Study first appeared on Premier Pits.]]>

The Project

Premier Pits were appointed in October 2016 to install a prefabricated vehicle pit. The original scope was to install the pit with in situ reinforced concrete. However, our client, who worked with us before installing vehicle inspection pits, discussed with the end user the benefits of prefabrication off site.

The Problem

The client was faced with a challenging below ground structure. They highlighted the railway inspection pit as high risk on their risk register. It was on their critical path and therefore any delay on site would impact the end date. There was also a tolerance in the specification of +-5mm which they were unsure they could construct with insitu concrete. Not only this but they faced a skilled shortage of subcontractors who had the ability to construct this type of below ground structure in an on-site environment.

Solution

To mitigate the risk, they approached Premier Pits to investigate a prefabricated off-site approach. We collaborated with Buckingham Group and gave them a product with was commercially competitive with in-situ poured concrete short term. However, gave the end user a far superior product long term due to it being watertight, maintainable, cleaner and safer to use. It was also installed in 2 weeks reducing their anticipated programme time by over 6 weeks. The product is also fully painted and has LED lights making this an excellent working facility for their engineers.

Outcome

A satisfied main contractor and end user to have this facility, with cost, quality and time certainty during the build.

Testimonial

“We have worked with Premier Pits on several road vehicle maintenance pit projects and are therefore fully aware of all the benefits of prefabricated pits built off-site, this method of construction saved us considerable time on site and leaves the client with a far superior end product”.

Nigel Graveson, Project Director for Buckingham Group

Client Details

Client: Buckingham Group

Location: Alstom Technology Centre, Widnes

Specification

Manufacturing and installing a 30m Railway Inspection Pit. With LED lights and 2no. access tunnels.

No helpful answer? Call our support team.

+44 (0) 1775 821222

The post Railway Technology Centre Case Study first appeared on Premier Pits.]]> Underground Rail Maintenance Case Study https://www.premierpits.com/portfolio-posts/underground-rail-maintenance-case-study/ Mon, 04 Sep 2017 08:37:23 +0000 https://www.premierpits.com/?post_type=portfolio&p=1372 To install prefabricated steel maintenance pits for the passenger transfer system at Heathrow’s Terminal 5.

The post Underground Rail Maintenance Case Study first appeared on Premier Pits.]]>

The Project

To install prefabricated steel maintenance pits for the passenger transfer system at Heathrow’s Terminal 5.

The Problem

The pits had to be installed 12m below ground level without interfering with other ongoing construction work. Also, the pits had to allow for free access along the length of the pit when in day to day use.

Solution

Due to restricted site access, the pits had to be designed in 8 metre sections prior to manufacture at Premier Pits’ factory in Spalding. They were then delivered by road direct to site. On arrival, the sections were offloaded and lowered by crane in one movement through the terminal roof, into position 12metres below ground level. Here they were bolted together to form 54 metre long water tight pits.

The problem of continuous access was answered by designing supports that only projected halfway across the width of the pits.

Outcome

Both pits were installed within 10 working days during which there was minimum disruption to other construction work. The pits are now operational and are playing a significant part in improving maintenance efficiency and staff working conditions.

Client Details

Client: Balfour Kilpatrick

Location: London Heathrow Terminal 5

Specification

Two 54 metre pits manufactured from pre-formed mild steel, fitted with safety lights and anti-slip flooring with a durable paint finish.

No helpful answer? Call our support team.

+44 (0) 1775 821222