Inspection Pits | Premier Pits https://www.premierpits.com Garage Pits Wed, 09 Apr 2025 14:40:30 +0000 en-GB hourly 1 https://wordpress.org/?v=5.8.10 Why You Should Choose A Premier Pits Full Installation https://www.premierpits.com/portfolio-posts/__trashed/ Mon, 01 Jul 2019 15:35:46 +0000 https://www.premierpits.com/?post_type=portfolio&p=1941 11 good reasons why you should let Premier Pits install your pit No-one cares as much as Premier Pits to install your pit correctly. Experience is everything. We install 4 pits a week and have installed over 3,500 in the UK, Ireland, Norway, France, Angola and Afghanistan. Premier Pits know all the tricks of the […]

The post Why You Should Choose A Premier Pits Full Installation first appeared on Premier Pits.]]>
11 good reasons why you should let Premier Pits install your pit

  1. No-one cares as much as Premier Pits to install your pit correctly.
  2. Experience is everything. We install 4 pits a week and have installed over 3,500 in the UK, Ireland, Norway, France, Angola and Afghanistan.
  3. Premier Pits know all the tricks of the trade for pit installations which can save you time and money.
  4. 75% of Supply Only sites without Premier Pits full installation service experience problems with the installation, creating uncertainty which results in a cost in both time and money.
  5. Almost all main contractors employ Premier Pits to install the pit on their new site, even when they have all the plant and labour.
  6. A single Premier Pit installation takes on average just 5 days. We are onsite on the agreed date.
  7. A Premier Pits full installation allows you to carry on with the day to day running of your business.
  8. All Premier Pits Installation Team members are fully employed by the company, on PAYE and included in the company profit share scheme, meaning they have a vested interest in your pit purchase.
  9. You will only save money doing Supply Only if you have your own labour and plant.
  10. When the client digs the hole, it mostly results in having to buy more concrete.
  11. Most pit manufacturers push Supply Only because they don’t have the resources, knowledge or experience to take on installations.
The post Why You Should Choose A Premier Pits Full Installation first appeared on Premier Pits.]]>
Pit Replacement Case Study https://www.premierpits.com/portfolio-posts/pit-replacement-case-study/ Thu, 14 Sep 2017 10:41:41 +0000 https://www.premierpits.com/?post_type=portfolio&p=1451 To dig out 10 old pits and replace them with 9 new pits within a 12 week period, whilst the workshop was still under 24 hour operation.

The post Pit Replacement Case Study first appeared on Premier Pits.]]>

The Project

To dig out 10 old pits and replace them with 9 new pits within a 12 week period, whilst the workshop was still under 24 hour operation.

The Problem

The garage needed to install new pits due to bus design changes such as lower floors affecting under body access and the change in the size of modern buses. It was not an option to close down the workshop whilst the project took place, the replacements went ahead in a 24 hour fully operational workshop. The waste away generated had to be cleared on a daily basis to keep the workshop as clear as possible.

Solution

To keep the workshop disruption to a minimum, Premier Pits worked on sections of 3 or 4 pits at a time. Each pit was broken out individually and replaced with a new one before moving onto the next. This approach made it possible for Premier Pits to work efficiently while Lothian the garage went about their day to day operations with minimum disruptions. The waste away generated is generally cleared after the dig outs have been completed, so to clear on a daily basis from this site caused extra time and labour but did not delay the project.

Outcome

The garage took out a complete pit replacement involving 10 old pits and 9 new pits without having to close down the workshop and within the 12 weeks period allocated.

Client Details

Client: Private PSV Company

Location: North East England

Specification

Nine working pits each 17 metres long; 1.25 metres wide and 1.65 metres deep.